Overturning Construction Project Delay Penalties Using Verified Weather Records
Developers try to enforce $10,000/day liquidated damages penalties when projects finish late. Discover how project managers prove excusable, non-compensable weather delays.
Amit KasliwalCEO & Founder, Dehurdle
February 18, 20234 min read

The Critical Path Weather Defense
Recommended Spoken Script
"Our baseline CPM schedule proves that structural steel erection was delayed by 18 days due to 45 mph sustained winds that legally prohibited tower crane operation under OSHA safety mandates. This constituted an excusable, non-compensable weather delay, entitling our team to a 18-day schedule extension with zero liquidated damages."